4.88MW Roof Distributed Photovoltaic Project of JCHC Suqian Tonghu Logistics Park Phase II Successfully Connected to the Grid
On April 16, 2025, the 4.88MW roof distributed photovoltaic project of JCHC Suqian Tonghu Logistics Park Phase II, invested and constructed by Jiangsu Communications holding Clean Energy Jiangsu Co., Ltd. and EPC contracted by Share Power Co., Ltd., successfully achieved full-capacity grid-connected power generation!
The project started construction on March 10, 2025. With the strong support and correct leadership of Jiangsu Yunnan Clean Energy Investment Holding Co., Ltd. and Jiangsu Tonghu Logistics Park Co., Ltd., and under the supervision of the supervision unit Jiangsu Hengjian Project Management Co., Ltd., Share Power Co., Ltd. carried forward its consistent tradition of being able to tackle tough tasks. It carefully arranged the design and procurement, overcame numerous difficulties such as tight equipment ordering and supply, and large-scale coordination of public municipal roads and green belts outside the park. In just 37 days, it smoothly completed the reverse power transmission, testing and other links, and achieved a one-time full-capacity grid connection on April 16, successfully completing the node target of April 30 ahead of schedule!
The total installed capacity of this project is 4.88 MW. During the operation period of the power station, the average annual on-grid electricity is approximately 6.29696 million kWh, the annual equivalent full-load operating hours are 1005.16h. It can save about 1,865 tons of standard coal and reduce carbon dioxide emissions by 4,651 tons every year, with remarkable energy-saving and emission-reduction effects.
Share Power Co., Ltd. will create more brilliant achievements in the new energy field and contribute more to building a beautiful China and achieving the goal of sustainable development!